Rail Creek

On May 12, 2025, the City Council approved a contract with Vireo LLC to begin work on the Rail Creek Master Plan and Market Analysis. This nine-month project will explore development opportunities for the property located at 6103 Woodland Drive.

Below is the approved project timeline. Stay tuned for updates and ways to share your input on this exciting new opportunity in Shawnee!
  • May 12, 2025: Approve consultant agreement
  • May - June 2025: Background phase
  • June - August 2025: Site studies phase
  • September - October 2025:  Master Plan refinement
  • November - December 2025: Draft Master Plan
  • January - February 2025: Final Master Plan for Council Approval