Monticello Road – Johnson Drive to 66th Street, P.N. 3321City Staff Contact:
Paul Lindstrom (913) 631-2500 x 234 Project Description: This project involves the widening of Monticello Road from 2 lanes to 4 lanes between Johnson Drive and 66th Street. This will include adjustment of storm sewer facilities, new curb, adjustment of street lights, a new bridge structure at Clear Creek, pavement markings, and signing. Project Status: This project is scheduled for construction beginning summer 2009. The City anticipates design to begin summer 2008. Monticello, Midland to 7900 Block, P.N. 3322
City Staff Contact:
Paul Lindstrom (913) 631-2500 x 234 Project Description: This project involves the reconstruction of Monticello, from Midland Drive to the 7900 Block. The improvements will include new pavement, storm drainage facilities, curb, sidewalk on both sides, street lighting, recreational trail, signing and pavement markings. Project Status: This project was discussed at the November 13, 2006 City Council meeting to approve construction of a 4-lane roadway, with a recreational trail on the west side and a sidewalk on the east side between Midland Drive and 75th Street. There will be on-street bike lanes between 75th Street and the 7900 block. The consultant presented two different alignment options at a neighborhood meeting on Wednesday, January 24, 2007. This information was presented at the February 12, 2007 City Council meeting and Option 2 was approved the alignment that will offset Monticello 12 feet to the west, from approximately 800 feet south of Midland to the 7000 block, and a 20 foot offset to the east, from approximately 7030 Monticello to 200 feet south of 71st Terrace. The preliminary plans were approved at the May 14, 2007 City Council meeting. The consultant is working on final plans. Easement acquisition has begun. Construction is expected to begin Fall 2008. Before a date is set for bidding, the final plans will be brought to a public meeting and then sent to the City Council for approval. Some utility relocation work will commence prior to road construction beginning. Silverheel Street – Clear Creek Parkway to 66th Street, P.N. 3325City Staff Contact:
Paul Lindstrom (913) 631-2500 x 234 Project Description: This project involves the construction of a new street (Silverheel) along K-7 Highway connecting from the existing development along 66th Street, west and north to the existing roundabout at Woodsonia Drive and Clear Creek Parkway. This will include new pavement, curbs, sidewalk on one side, street lights, storm sewer facilities, a new pedestrian bridge structure across Clear Creek, a new roundabout at Clear Creek Parkway and Silverheel, pavement markings, and signing. Project Status: This project is scheduled for construction beginning fall 2008. The consultant is working on the study and report. Silverheel Street – 69th Block to 71st Street, P.N. 3326City Staff Contact:
Paul Lindstrom (913) 631-2500 x 234 Project Description: This project involves the construction of a new street (Silverheel) along K-7 Highway connecting from the existing development at the 6900 block, south to the existing 71st Street. This will include new pavement, curbs, sidewalk on one side, street lights, storm sewer facilities, pavement markings, and signing. Project Status: This project is scheduled for construction beginning summer 2008. The consultant is working on the final plans. 57th Terrace – King to Barton, P.N. 3341City Staff Contact:
Paul Lindstrom (913) 631-2500 x 234 Project Description: This project involves the reconstruction of 57th Terrace between King and Barton Avenue. This will include new pavement, storm sewer facilities, new curb, street lights, pavement markings, and signing. The project will tie into improvements recently completed on King Street. Project Status: This project is scheduled for construction beginning May 1, 2008. Johnson Drive and Roberts Roundabout, P.N. 3345City Staff Contact:
Paul Lindstrom (913) 631-2500 x 234 Project Description: This project involves the construction of a new roundabout at the intersection of Johnson Drive and Roberts Street. This will include widening of pavement, curbs, sidewalk on one side, adjustment of street lights, storm sewer facilities, and installation of pavement markings and signing. Project Status: This project is scheduled for construction beginning Fall 2008. The consultant is working on the study and report. K-7 and Johnson Drive/55th Street Interchange Improvements
The Kansas Department of Transportation (KDOT) and the City of Shawnee conducted a public meeting on February 22, 2007. Above are the informational links about that public meeting. Background: In 2004, KDOT and the City of Shawnee studied potential improvements at the intersection of K-7 and Johnson Drive/55th Street. The study concluded that the current at-grade, signalized intersection is inadequate to handle anticipated traffic levels from rapid development in the area. It also reviewed three alternatives for handling anticipated future traffic growth and identified the preferred concept as a roundabout interchange with a second roundabout built west of K-7, at the intersection of Hedge Lane Terrace and 55th Street.
|